On a busy weekend, Spooky Nook Sports may host 300–400 teams, along with parents and guests. Late games can keep teams on the courts beyond 10:00 p.m., leaving very little uninterrupted time for floor work.
The challenge was to prepare and apply two maintenance coats across 10 hardwood basketball courts (approximately 50,000 square feet) within a three-day work window, while preserving enough time for drying, final cleanup and a safe return to full participation within one week.
Project details
- Customer: Spooky Nook Sports
- Location: Manheim, Pennsylvania
- Challenge: Heavy use and extremely limited downtime
- Americhem support: Project planning, tailored options and gym-floor expertise
- Scope: 10 hardwood basketball courts totaling approximately 50,000 square feet of floor area
- Coating coverage: Approximately 100,000 square feet across two maintenance coats
Watch the Spooky Nook Project From Start to Finish
Video not loading? Watch it on YouTube.
A high-traffic facility with almost no downtime
Spooky Nook Sports is a facility built for volume. Its Manheim complex contains more than 700,000 square feet under one roof and includes 10 hardwood basketball courts, along with spaces for volleyball, field hockey, soccer and other sports.
In Americhem’s project interview, Darren Hackenburg of Spooky Nook Sports described just how demanding the basketball schedule can be. During a busy weekend, approximately 300–400 teams may use the facility, along with their parents and guests. Court activity can run from 7:00 a.m. until 10:00 p.m. on Saturdays and Sundays, and teams playing late games may remain after 10:00 p.m. Weeknight use can extend from approximately 4:00 p.m. until 10:00 p.m.
That level of activity leaves little margin for a multi-day maintenance coat project. The challenge was finding and protecting enough uninterrupted time to prepare the floors, apply two maintenance coats, allow proper drying and safely reopen all 10 courts for full participation within one week.

Why Spooky Nook schedules a maintenance coat project every year
For Spooky Nook, appearance is only part of the equation. Its high-profile hardwood courts receive heavy use, and an annual maintenance coat project helps preserve the finished surface, protect the wood beneath, maintain traction for safe play and deliver the polished appearance expected of a competition facility.
Many gym floors are recoated about every two years, but Spooky Nook schedules a maintenance coat project annually because of the unusually heavy traffic and abuse its competition courts receive.
The right maintenance schedule should reflect actual use, floor condition and the role each space serves—not a generic date on the calendar. Some high-school competition floors may be recoated annually for protection, appearance and performance, while an elementary-school floor may follow a different schedule even when it experiences heavy multipurpose use.
The challenge: preparing and recoating 10 courts in three days
A maintenance coat project must account for more than active work time. Floor preparation, two maintenance coats, required drying time and final cleanup all had to be sequenced so the courts could safely return to full participation within one week.
Spooky Nook identified a narrow opportunity around Labor Day, when schools were returning to session and normal demand on the courts briefly eased. That provided a three-day window, Monday through Wednesday, to prepare all 10 courts and apply both maintenance coats.
Missing that window could have disrupted the facility’s packed schedule. The project required coordination before the first step began: evaluating the existing floor conditions, confirming the available options, coordinating labor and equipment, planning the sequence and protecting the required drying time.

The solution: expertise built around the customer's schedule
Americhem's role began with listening to what the facility needed.
Throughout the project, Americhem gym-floor specialist Scott Barnhart worked directly with the Spooky Nook team on planning, floor preparation, coating, equipment coordination and technical support. He aligned the work with the facility’s schedule, performance priorities and expectations for the completed courts. Darren highlighted Scott’s consistent support, technical knowledge and ability to present multiple options based on the facility’s needs.
That customer-first approach matters. No two gym floors experience exactly the same use, and no two facilities have the same maintenance window. The right recommendation has to account for the floor, traffic, available downtime and the people responsible for maintaining it after the project is complete.
By aligning the work with Spooky Nook’s operating schedule before the project began, the teams were able to prepare all 10 courts and apply both maintenance coats during the Monday-through-Wednesday work window while preserving the drying time needed for a safe reopening.

“It’s a really good partnership to be able to work with somebody that understands our needs and also has our best interests in mind.”
— Darren Hackenburg, Spooky Nook Sports
The result: 10 courts recoated in three days
The team prepared all 10 hardwood basketball courts and applied two maintenance coats during the planned Monday-through-Wednesday work window. After the finish dried, the team returned Thursday for final cleanup and project documentation, preserving the remaining time needed for a safe return to full participation within one week.
The scale of the work is impressive, but the more important result was the fit: the project addressed the facility's floor-care priorities without losing sight of its operational reality.
For Americhem, the project demonstrates what a true gym-floor partnership should look like—experienced guidance, options tailored to the facility and a plan designed around the customer's needs.

Five lessons for planning a gym floor maintenance coat project
The Spooky Nook project offers several useful takeaways for facility managers planning hardwood gym floor maintenance:
Start with the operating calendar. Identify school breaks, holidays, off-seasons or other periods when the floor can remain undisturbed for the complete project window.
Base maintenance frequency on real traffic. A heavily used tournament facility may need a different schedule than a smaller school gym.
Evaluate the floor before choosing the system. Current condition, previous coatings, performance goals and maintenance practices should guide the recommendation.
Protect the full project window. Include the time required for every stage of the work—not only application time—before reopening the floor.
Work with a specialist who offers options. The best plan is built around the facility rather than forcing every floor into the same process.
Gym floor support for schools and athletic facilities
Whether a facility has one school gymnasium or 10 tournament courts, Americhem can help develop a gym floor plan that fits its floors, staff and schedule.
Americhem supports K-12 schools, colleges and universities, recreation centers and athletic facilities with gym-floor maintenance planning, floor-care products, equipment recommendations and staff training. With locations throughout Pennsylvania and neighboring states, the team can help facilities plan maintenance coat projects and the routine care that protects hardwood floors between projects.
Frequently asked questions
The team prepared all 10 courts and applied two maintenance coats during a three-day work window, Monday through Wednesday. After the finish dried, the team returned Thursday for final cleanup and project documentation. This schedule preserved the remaining time needed for the courts to return safely to full participation within one week.
There is no single schedule for every facility. Many gym floors are recoated about every two years, but frequency should reflect traffic, current floor condition, the coating system, maintenance practices and performance expectations. Spooky Nook schedules a maintenance coat project annually because of the heavy use and abuse its competition courts receive and the facility’s goals for floor protection, appearance and safe play.
Many facilities schedule gym floor recoating during summer break, a holiday period or an athletic off-season. The important step is to reserve enough uninterrupted time for floor preparation, each maintenance coat and the required drying time before the floor safely returns to use. The best timing depends on the facility’s operating calendar.
Yes. Americhem can help facilities evaluate floor condition, plan maintenance coat projects, coordinate products and equipment, provide technical support and train staff on routine floor care. Recommendations are tailored to the floor, traffic, operating schedule and facility’s performance goals.